Red Clover TAC Meeting Minutes

April 13, 2005

Portola City Hall Council Room

 

Attendees:  Jim Wilcox, Leslie Mink, Gia Martynn- CRM Staff; Dennis Heiman, RWQCB; Todd Hillaire, DWR; Joe Hoffman, USFS; Lori Powers, CDF&G; Dan Martynn, NRCS; Scott Thompson, Goodwin Ranch

 

Jim handed out a project area map, cross-sections, and project progress summary.  Explained the Area of Potential Effects (APE), where direct effects are expected to occur and then the greater area designated for survey and contextual analysis purposes for archaeology and botany.  He then summarized the cross-sectional data collected to date.  Plans to try and access project area tomorrow, so we can get access for specialist survey work and continued cross-section surveys.  Hopes to get in and start x-section work by May/June, and then flag initial design layout.  Cows usually go on mid-May, but Scott is flexible.  Jim will coordinate with Scott to flag after cows are out to avoid cows eating the flagging.   

 

Contracts for botany, wildlife, and archaeology surveys have been advertised and bids are due April 15th.  Surveys for botany and arch will probably begin in June/July.  Wildlife surveys will begin as soon as possible for great gray owls and on into the summer for other species.  CRM staff will do amphibian surveys and help DWR with fish surveys in June. Potential resource conflicts will be addressed as the design evolves this summer/fall. 

 

Everyone in the water schedule for the Red Clover area will be notified of the project, as agreed to between Jim and the Curtis Levine, the water master.  Dan suggested that maybe additional users downstream, outside of the schedule but within the decreed area, should also be notified.  It was agreed that a letter and information would also be sent to Jerry Spurlock in Indian Valley.   

 

Leslie handed out a draft monitoring plan and discussed past and current (on-going) monitoring that affects Red Clover.  We then looked at what questions we want answered from pre- and post-project monitoring and decided on the following:

 

We did not set a date for the next meeting, but plan to schedule a field meeting sometime in early July to review the project layout and conceptual design alternatives.