|
Section 5
Streambank Stabilization
Purpose and Objective
The objective of the streambank stabilization
study was to test the effectiveness of several treatments in stabilizing
eroded streambanks within the demonstration area. Practical and cost-effective
techniques included structural measures (check dams), biological treatment
(revegetation), revision of land management practices (land management),
and reinforcement of streambanks with new nonstructural bio-geotechnical
methods (Gray and Leiser 1982).
Methods
Check Dams
Four loose rock check dams were constructed
at intervals in a half-mile reach of the stream to create a series of ponds
that would reduce flow velocity, channel gradient, and streambed downcutting.
A local rock outcrop was blasted to obtain 2,520 cubic yards of rockfill
material for the dams (USDA SCS 1985). Local soils were compacted to form
watertight cores in the dams. Each upstream dam was constructed 3–4 feet
higher than its downstream neighbor to form a series of steps in pond elevation,
with the head of each pond submerging the toe of the next dam upstream.
Since they were built at points determined by channel gradient and location
of bedrock anchor points, their spacing is irregular (Figure 5-1). The
distances between Check Dams #1, #2, and #3 were relatively short, indicating
a steeper stream gradient; the distance between Check Dams #3 and #4 was
long, indicating a much flatter gradient. The overall height of each dam
was in the range of 5–10 feet as measured from the keyway foundation to
the highest part of the abutments.
The dam designs were developed in accordance
with SCS design standards, with some structural modifications to make them
more secure (USDA SCS 1985). The dams were keyed into the banks approximately
10 feet (further than required by the standard) to ensure against washout
of the abutments. The downstream aprons of the spillways were graded at
approximate slopes of 10:1 (the standard design required 5:1). The flatter
and longer aprons provided much more energy dissipation to protect against
erosion at the downstream toes of the dams and greater stability against
movement of dam materials by high flows (Figure 5-1)
Spillway cross-sections at the dams
were sized to accommodate a ten-year flood flow. At Check Dams #3 and #4,
where the banks were relatively low, earthen dikes were extended from the
dams onto the floodplain to divert flows away from the dam abutments in
the event that high flows overtopped the dams and banks. The ponds reduce
the velocity of the flow, which decreases the erosional energy of the water
and causes deposition of suspended sediments. The dams also immediately
raise the elevation of the shallow water table out into the floodplain,
increasing aquifer storage capacity and creating more desirable growing
conditions for plants (see Section 13 for more details).
Revegetation
A revegetation plan was implemented
to accelerate the recovery of vegetation in areas impacted by construction
of the check dams and to reintroduce desired woody and herbaceous species
into the plant community. A key project objective was to test the feasibility
of reestablishing native species where possible. Planting took place in
the study area in fall 1986 and spring 1987 (Figure 5-2). Treatment variables
included several hardwood plant species (unrooted cuttings and rooted liners),
two planting seasons (fall and spring), and three zones of available moisture
(high, medium, and low) based on elevation above the water table (Table
5-1). Two herbaceous seed mixes were also tested (Table 5-2). Lindquist,
McCalla, and Filmer (1994) provide detailed planting and monitoring results.
Woody plantings along the streambanks
consisted of unrooted cuttings of locally obtained coyote willow and black
cottonwood and rooted nursery stock (liners) of several hardwood species
(Table 5-1). Rooted liners were planted on the top of banks; unrooted cuttings
were staked into vertical bank faces and bank toes and along rock keyways.
Two herbaceous seed mixes were tested—a
commercial mix of crested and intermediate wheatgrasses and alfalfa and
a mix of native western wheatgrass and Great Basin wild rye (Table 5-2).
The seed mixes were broadcast on top of the banks and construction areas,
fertilized, raked, and in some areas mulched with straw (Figure 5-2). This
presented an opportunity to test the survival rate of native species over
a commercial seed mix in stabilizing denuded areas.
Monitoring data were collected in 1987,
1988, and 1994 to determine the most successful planting treatments in
terms of survival and overall cost. Surviving woody plants were counted
each August by species, plant form, moisture zone, and planting season.
Percent cover of herbaceous vegetation grown from seed mixes was estimated
visually. In 1994, field observations were made to provide qualitative
assessment of the results after seven years.
Table 5-1
Evaluation of Revegetation Plantings
with Hardwood Species After Two Growing Seasons
| Unrooted Cuttings (Local)b |
Rooted
Liners (Off Site)b |
|
Planting
Season |
Moisture
Zonea |
Black
Cottonwood |
Coyote Willow |
Quaking
Aspen |
Mtn
Alder |
Willowc |
Black
Cottonwd |
Douglas
Spiraea |
| Fall 1986 |
High |
G |
E |
N/A |
N/A |
N/A |
N/A |
N/A |
| Fall 1986 |
Medium |
G |
G |
P |
P |
N/A |
N/A |
N/A |
| Fall 1986 |
Low |
P |
G |
P |
P |
N/A |
N/A |
N/A |
|
|
|
|
|
|
|
|
|
| Spring 1987 |
High |
G |
G |
G |
P |
P |
G |
P |
| Spring 1987 |
Medium |
N/A |
P |
G |
P |
P |
P |
P |
| Spring 1987 |
Low |
N/A |
P |
P |
P |
P |
P |
P |
Source: Lindquist, McCalla, and Filmer,
1994, Erosion Control Demonstration Project in Red Clover Valley: Revegetation/
Streambank Stabilization Program.
N/A = Not applicable. No planting
in that zone.
a High moisture zone (wet)
= 0–2 feet, medium moisture zone = 2–4 feet, low moisture zone (dry) =
>
4 feet.
bSuccess rates: E = excellent,
G = good, P = poor.
cThree liner willow species
include Columbia River willow, coyote willow, and purple osier willow.
Woody Species Planted in the Demonstration Area
Common Name
mountain alder
red osier dogwood
quaking aspen
black cottonwood
coyote willow
Columbia River willow
purple osier willow
douglas spiraea
|
Scientific Name
Alnus tenuifolia
Cornus stolonifera
Populus tremuloides
P. trichocarpa
Salix exigua
S. fluviatilis
S. purpurea
‘streamco’
Spiraea douglasii
|
Table 5-2
Herbaceous Seed Mixes Planted in
Demonstration Area, April 1987
| Seed Mix |
Species |
Planting Success |
| Commercial |
crested wheatgrass (Agropyron desertorum
Nordan)
intermediate wheatgrass (A. mediumOahe)
alfalfa (Medicago sativa Ladak) |
Excellent in the first year |
| Native |
western wheatgrass (A. smithii)
Great Basin wild rye (Elymus cinereus) |
Fair after three years |
Source: Lindquist, McCalla, and Filmer,
1994, Erosion Control Demonstration Project in Red Clover Valley: Revegetation/
Streambank Stabilization Program.
Note: All planting done in the high
moisture zone.
Land Management and Controlled Access
An exclosure fence consisting of five
strands of barbed wire was constructed around approximately 65 acres. The
fence prevented cattle and vehicle disturbance to vegetation, soils, and
check dams within the project area. The original landowner agreed not to
graze the exclosure area until 1991 (five years) but voluntarily deferred
grazing until 1994, when a grazing plan developed by FRCRM and the new
landowner was put into effect. The plan prescribed short-duration grazing
(five days) within the exclosure to increase plant vigor and stimulate
new growth. Grazing was planned for late season (August) to avoid conflict
with waterfowl nesting. After eight years of protection from grazing, grasses
and willows were thriving along the channel and in low-lying areas of the
meadow within the fenced area. In contrast, intense cattle grazing outside
the exclosure removed most of the vegetation, leaving soils vulnerable
to erosion.
Bio-Geotechnical Treatments
Two bio-geotechnical treatment methods
were undertaken to demonstrate the effectiveness of nonstructural, less
costly restoration treatments. The methods were selected based on cost,
feasibility, and the availability of local materials. The first was installation
of a cut-tree revetment at the north bank of Pond #1 in 1987 and 1988 (Figure
5-3). Small Jeffrey Pines were placed butt-up along the face of the bank
and secured to the top of the bank with cables (Sheeter and Claire 1981).
The trees were expected to reduce water velocity, protect the streambank
from erosion, and filter and deposit sediment, thereby allowing vegetation
to establish. The second method was reinforcement of an eroding bank with
willow matting (locally collected plant stock tied together to form a mat
structure). The mat was then

staked down with heavy wire along the
south bank of Pond #1 in 1991 to arrest erosion where strong currents impinged
during high flows.
Key Findings
Check Dams
-
The check dams were effective in slowing
the water velocity through the project site during high flows, thereby
reducing the erosive forces on the stream bottom and banks. This gave the
revegetation measures a better chance of success and reduced local recruitment
of sediment to the stream. The upper dam required maintenance after the
seventy-five-year flood event in 1986, but otherwise survived several subsequent
twenty-five-year events with minimal effect.
-
Check Dam #2 appeared to cause currents
to form on the north bank upstream of the dam; the currents eroded the
south bank of Pond #1, which damaged the willow matting. Some care is required
in the layout and design of check dams to ensure that jet flow downstream
of the spillways does not impinge on erodible banks and is consistent with
geomorphologic features of the system.
-
The check dams were also effective in
raising the elevation of the stream, which over time led to seasonal recharge
of the shallow water table. This had a very positive effect on establishment
and growth of vegetation along the channel and far out on the floodplain
and, along with the exclosure fence, was largely responsible for the quick
site recovery and dramatic increase in waterfowl use.
-
Check Dam #4, heightened by a beaver addition,
caused overland flow during high flows, which, upon reentry to the main
channel below Check Dam #1, caused bank failure and headcutting of an old
shallow channel. Again, careful attention to design of the check dams is
required to address this potential problem. Where overland flow is likely,
reentry points need to be identified and armored if necessary to prevent
bank erosion and/or headcutting.
Revegetation
-
Many plants established reasonably well,
in spite of persistent drought. Overall survival of woody species was 44%
during the first year (1987) and 23% during the second year (1988). Fall-planted
unrooted cuttings, however, had consistently higher survival rates than
rooted liners for most combinations of treatments—33% survival for stakes
and only 17% for liners after the second growing season (Figure 5-4). Spring
plantings showed similar survival rates for both stakes and liners after
two growing seasons; based on a 1994 monitoring survey, survival rates
for unrooted stakes were higher than rooted liners for all treatments.
Continued drought severely desiccated rooted liners. Plantings in the highest
moisture zone (0–2 feet from the water table or surface water) were most
successfully established regardless of species or plant type (Table 5-1,
Figures 5-5 and 5-6).
-
Overall, locally collected unrooted willows
planted in the fall in the high-moisture zone were most successfully established,
even in rocky sites along the dam keyways. Planting unrooted stakes provides
several advantages over rooted materials, including lower cost to obtain
materials because they are collected locally, less time required to install
per plant, less stress of acclimation because they are already adapted
to local climatic conditions, broader moisture tolerance due to their 18-24
inch length, lack of an initial root structure to support, and ability
to survive on sloped and flat areas. Willow stakes can survive up to three
years on carbohydrate reserves alone and therefore tend to be more drought-resistant
than rooted materials.

-
Results after the first year of planting
were not necessarily indicative of what plant type and season showed the
most promise. Overall, results between treatments (i.e., fall vs. spring
planting and liners vs. stakes) were not appreciably different after the
first year, but these numbers changed dramatically after the second and
third growing seasons. Therefore, monitoring for at least three years is
recommended to compare treatments more accurately.
-
For best results, unrooted stakes should
be collected and used while dormant and should be cut as long as possible
(24–36 inches) based on site conditions. This improves access to deeper
water. In rocky areas, stake plantings should be preceded with a pilot
hole to avoid damage to the bark while planting. Willow stakes should be
soaked for 48 hours before use to dissolve rooting inhibitor hormones.
-
Drought conditions and climatic variability
were the overriding factors affecting plant survival, especially in the
first three years after planting. Soil moisture was a critical factor.
Better survival rates were achieved in the high- and medium-moisture zones
(Table 5-1, Figures 5-5 and 5-6).
-
Of the rooted liner species, quaking aspen
had the best results compared to mountain alder, black cottonwood, and
douglas spirea, which did poorly (Table 5-1). Rooted liners are sensitive
to weather variations and require planting in high-moisture zones; alternatively,
irrigation may be required to establish the plants. They were also more
labor-intensive to plant and more costly overall. Rooted liners used in
this study were obtained from a nursery in Oregon and were therefore not
acclimated to site conditions. This could partially account for their poor
performance.
-
Mortality rates were higher than expected
for all species in this study due to, among other factors, prolonged drought
during the study period, planting before plants were dormant in some cases,
extreme climate variability, streambank sloughing, poor condition of some
liner plant materials, beaver activity, and planting species in low-moisture
zones where they would be unlikely to survive. Additional information on
natural regeneration of vegetation is presented in Section 8.
-
Initial seeding results were more successful
with the commercial seed than the native plant mix. Cover increased to
50% the first year with the commercial mix, providing more immediate erosion
protection to barren banks and berms. The native seed mix was slow to produce
results, but after three years, Great Basin wild rye was well established
on a dryer site away from the channel. Western wheatgrass establishment
was poor even after three growing seasons (Table 5-2). The lag time for
establishing native species should be taken into consideration when planning
future projects. Planting of native species is important to establish sustainable
long-term grass coverage. It is also important to obtain locally harvested
seed materials to promote more successful germination and establishment.
-
Planting of woody species on raw over-steepened
or vertical streambanks should be deferred at least two years following
a project due to sloughing of the banks. Mechanically sloping back streambanks
would reduce sloughing and accelerate revegetation and stabilization, but
it is costly and in many cases not feasible. Natural vegetation regrowth
was extensive after the third growing season, once the channel began to
stabilize and the water table was recharged.
-
Impact of cattle, beaver, and humans must
be controlled until new plants pass at least three growing seasons to provide
the best conditions for successful establishment. In 1994, beaver impact
was severe in some locations (mature willows were decimated by the beaver
population). Tours of the project in vehicles and on foot also caused some
plant mortality and must therefore be controlled.
-
A survey of plant survival conducted in
1994 showed that natural regrowth of vegetation was filling the gaps between
surviving planted vegetation. Point bars and the toe along the streambank
were well vegetated. Willows planted in keyways and along earthen berms
were surviving and firmly established, whereas most plants within the channel
were dislodged due to bank sloughing. Of the rooted liners, only a few
aspen survived. The commercial seed mix was well established and provided
good protection for soils disturbed in construction; alfalfa was frequently
used by deer and small mammals for food and cover. Of the native grass
seed mix, only the Great Basin wild rye survived and was thriving in pockets
of dry sandy soils away from the channel.
Land Management
-
The exclosure fencing kept cattle and
motorized vehicles out of the demonstration area for eight years. Though
infrequent, trespass by vehicles and even extensive foot traffic caused
mortality of some vegetation planted in the exclosure. The reduction of
disturbance helped establish vegetation and stabilize streambanks. The
flourishing hardwoods (willows) and herbaceous vegetation (grasses and
sedges) provided protection to soils and habitat for waterfowl and wildlife
and produced a stark contrast to barren ground outside the exclosure.
-
A grazing management plan reintroduced
controlled cattle grazing in the exclosure in 1994. Unfortunately, cattle
remained in the exclosure for several weeks, denuding most vegetation and
trampling streambanks. In response, the FRCRM Grazing TAC developed draft
guidelines for grazing management at future projects. Identification of
improved land management practices is a key component of successful watershed
restoration and should be built into projects in the initial stages of
planning. Site visits in 1995 confirmed that significant vegetation regrowth
did occur in the exclosure, but mechanical damage to streambanks from cattle
trampling was still apparent and slower to heal.
-
Due to reduction in grazing at the downstream
control site, remarkable improvement was observed after 1989. The creek
showed marked signs of healing without any other measures being undertaken.
At this location, the channel narrowed and began to meander, riparian vegetation
reestablished along the banks, fish became established, and bank stability
improved. In some instances, changes in land management alone can turn
around the degradation process, albeit at a slower rate.
Bio-Geotechnical Treatments
-
The cut-tree revetment was effective in
promoting stabilization of the north bank of Pond #1. The revetment filtered
sediment that deposited at the base of the streambank. This provided substrate
for establishment of vegetation, which in turn enhanced stabilization.
This area is continuing to heal, and sedges and willows are firmly established.
Though juniper tends to resist decay and has a more desirable structure
for stream revetment purposes, Jeffrey Pine held up remarkably well after
ten years of exposure and is therefore recommended in the absence of juniper.
-
Willow matting installed at the south
bank of Pond #1 did not halt erosion. The mats were probably washed out
by high flows before they had a chance to take root and develop sufficiently
to provide erosion protection. The matting was prepared before willow stakes
were dormant, possibly causing stress. In addition, return flow from the
overtopping of Check Dam #4 reentered the channel on top of the matting
(between Check Dams #1 and #2), undermining the matting (see Figure 3-3).
Variations of this technique have proved successful at other projects in
the watershed. Such structures must be designed and sited with care to
maximize success.
Table of Contents
|